Upcoming work
Construction continues along the Creek Trail, with active work zones throughout the project area. Here's what you can continue to expect over the next two weeks:
- Steel fence post installation from Date to Ash Streets
- Wayfinding sign installation between Broadway Avenue and Ash Street
- Irrigation work from Fig to Rose Streets
- Cable railing installation and fence removal from Fig to Ash Streets
- Trenching for electrical conduits from Rose Street to Midway Drive
- Grading and placing gravel base (Class II base) Date to Ash Streets
Construction will pause for the July 4th holiday, but equipment and materials will remain on-site. Please continue to use caution when passing through the area.
Trail users should anticipate the following impacts:
- Periodic short-term closures during irrigation and fence work.
- Cable railing work will require 24-hour closures for public safety, with each section taking 4–5 working days to complete.
Please pay attention to road signs in the area for the most up-to-date information on Creek Trail access.
Recently completed
Crews continue to make steady progress along the Escondido Creek Trail, completing several key improvements over the past few weeks:
- Installation of cable railing between Broadway Avenue and Juniper Street and Hickory and Fig Streets. This section of the trail is now reopened to the public.
- Steel fence installation between Broadway Avenue and Date Street on the north trail.
Open during construction
Businesses along the Creek Trail Corridor remain open during construction and appreciate your support — so be sure to stop by and shop locally throughout the year.
Contact us
We appreciate the community’s patience as we work on this important project. Reach out to the project team if you have any feedback or questions. A team member will get back to you in two (2) business working days.
- Phone: Call us at 760-839-4949
- Email: Email questions or feedback to creek@escondido.org
- Regular updates: Subscribe here for regular updates.
- For additional information, please visit the Escondido Creek Trail webpage.
About the project
Construction for the Escondido Creek trail began in February 2025. Work will take place from Citracado Parkway to North Midway Drive, with construction generally moving from west to east. The project is expected to be completed in late 2025, pending any unforeseen delays. Construction hours are Monday through Friday from 7 a.m. to 4:30 p.m., with the exception of city-recognized holidays.